Construction Estimate
High rise building is supported on a reinforced raft concrete foundation. Calculate the cost per cubic metre to supply and place concrete using a concrete pump at a price of $295 per hour including an operator and a crew consisting of 5 labourers ($31/hour each), a cement fisher ($39/hour) and a foreman ($40/hour). With this set up concrete is placed in 7 hours and the transportation and set up of the pump costs $290. The work consists of supplying and placing 112 cubic metres ($180/cm) of concrete into the footings. Calculate the unit rate for each of the labourer, material and equipment per cubic metre as well as a total cost per cubic metre.
![Maggie](https://matchmaticians.com/storage/user/101872/thumb/AATXAJxmTXCs7skdvMlxZr3BkFwO7A_sGcxI5cstpKzozw=s96-c-avatar-512.jpg)
Answer
- The questioner was satisfied with and accepted the answer, or
- The answer was evaluated as being 100% correct by the judge.
![Erdos](https://matchmaticians.com/storage/user/100028/thumb/matchmaticians-3empnt-file-5-avatar-512.jpg)
-
As the other user mentioned your bounty was low for this question, but I decided to answer as I thought this might be the first time you are asking a question on the website. Please offer higher bounties for your future posts.
- answered
- 537 views
- $2.93
Related Questions
- Fluid Mechanics - algebra
- Certain isometry overfinite ring is product of isometries over each local factor
- Set theory question
- How old is the wise man?
- If both $n$ and $\sqrt{n^2+204n}$ are positive integers, find the maximum value of $𝑛$.
- Multiplying Polynomials
- Find the coordinates of the point $(1,1,1)$ in Spherical coordinates
- Element satisfying cubic equation in degree $5$ extension
It would take about 25-30 minutes to write a good solution. Your offered bounty is low!